GUN CLUB ROAD DATA CENTER PHASE 2 - CONDITIONAL USE, SITE PLAN AND REPLAT | Need Tech Subm
Type Phase Title Date Resubmit View
Case Files - 2nd Technical Review Comments Need Tech Subm2nd Technical Review Comments11/19/2024
Site Plan - Site DetailsNeed Tech SubmQTS Aurora PH2 - 4th Round Comment Response10/29/2024
Case Files - 1st Technical Review Comments Need Tech Subm1st Technical Review Comments8/26/2024
Site Plans - Architectural ElevationsNeed Tech SubmQTS PH2 - Letter of Introduction8/13/2024
Site Plans - Fence PlansNeed Tech SubmQTS PH2 - 3rd Round CRL8/13/2024
Site Plans - Sign PlansNeed Tech SubmParcel Map Check Report8/13/2024
Site Plans - Alta SurveyNeed Tech SubmPlat Greenline Responses8/13/2024
Case Files - Planning Commission Results Letter Need Tech SubmPlanning Commission Results Letter7/25/2024
Case Files - Document OnePlanning File MgmtLetter of Introduction7/5/2024
Case Files - 3rd Review Comments Need Tech Subm3rd Review Comments6/17/2024
Case Files - CorrespondenceNeed 3rd SubmPlat - Response to Comments5/23/2024
Oil & Gas - Letter of IntroductionNeed 3rd SubmLetter of Introduction_updated5/23/2024
Case Files - Applicant Response - 3rd Review Comments Need 3rd SubmComment Response Letter5/23/2024
Case Files - 2nd Review Comments Need 3rd Subm2nd Review Comments12/15/2023
Case Files - Applicant Response - Technical Review Comments3Need 2nd SubmPlat - Resp to Comments10/23/2023
Case Files - Applicant Response - Technical Review Comments2Need 2nd SubmTraffic Letter - 1st Review - Resp to Comments10/23/2023
Case Files - Applicant Response - 2nd Review Comments Need 2nd SubmOperation Letter - Responses10/23/2023
Case Files - Applicant Response - Technical Review Comments1Need 2nd SubmLetter of Intro - Resp to Comments10/23/2023
Site Plans - Utilities PlanNeed 2nd SubmUtility Letter10/23/2023
Case Files - Applicant Response - 1st Review Comments Need 2nd Subm1st Round - Comment Response Letter10/23/2023
Site Plans - Traffic Impact ReportNeed 2nd SubmTraffic Study Letter10/23/2023
Oil & Gas - Noise Management PlanNeed 2nd SubmNoise Study10/23/2023
Case Files - Letter of Introduction/JustificationNeed 2nd SubmLetter of Intro10/23/2023
Site Plans - Operations PlanNeed 2nd SubmOperations Plan10/23/2023
Case Files - 1st Review Comments Need 2nd Subm1st Review Comments9/14/2023
Case Files - Acceptance Letter1st Referral SentAcceptance Letter8/24/2023
Case Files - Referral Memo1st Referral SentReferral Memo8/24/2023
FDPs - Tab1Submit ApplicationNoise Study8/9/2023
Site Plans - Preliminary Drainage Checklist City Review Submit ApplicationPDR Checklist8/9/2023
Master Plan - Master Utilities PlanSubmit ApplicationUtility Demand Letter8/9/2023
Case Files - Vicinity MapSubmit ApplicationCert of Taxes Due8/9/2023
Case Files - Title WorkSubmit ApplicationTitle Work8/9/2023
Case Files - Legal DescriptionSubmit ApplicationLegal Descript8/9/2023
Site Plans - Mineral Right AffidavitSubmit ApplicationMineral Rights Aff8/9/2023
Case Files - Response to Pre-app notesSubmit ApplicationResponse to Pre-App Notes8/9/2023