Case Files - 2nd Technical Review Comments | Need Final Mylars | 2nd Technical Review Comments | 3/1/2024 | | | | | | | | |
Site Plan - Cut Sheets | Need Tech Subm | Closure Report | 2/16/2024 | | | | | | | | |
Site Plan - Public Art Plan | Need Tech Subm | Monument Records | 2/16/2024 | | | | | | | | |
Case Files - Applicant Response - Technical Review Comments3 | Need Tech Subm | Plat Comment Response | 2/16/2024 | | | | | | | | |
Case Files - Applicant Response - Technical Review Comments2 | Need Tech Subm | ISP Comment Resposne | 2/16/2024 | | | | | | | | |
Case Files - 1st Technical Review Comments | Need Tech Subm | 1st Technical Review Comments | 12/21/2023 | | | | | | | | |
Site Plans - Operations Plan | Need Tech Subm | Comment Response | 12/4/2023 | | | | | | | | |
Site Plans - Public Improvement Plan | Need Tech Subm | Closure Report | 12/4/2023 | | | | | | | | |
Case Files - Administrative Decision Results Letter | Need Tech Subm | Administrative Decision Results Letter | 11/1/2023 | | | | | | | | |
Case Files - Document One | Need Tech Subm | Fourth Review Comments | 10/12/2023 | | | | | | | | |
Site Plans - Grading Plan | Need 3rd Subm | Closure | 9/7/2023 | | | | | | | | |
Site Plans - Utilities Plan | Need 3rd Subm | Monument Records | 9/7/2023 | | | | | | | | |
Case Files - Applicant Response - 3rd Review Comments | Need 3rd Subm | ISP and Plat Comment Responses | 9/7/2023 | | | | | | | | |
Case Files - 3rd Review Comments | Need 3rd Subm | 3rd Review Comments | 8/3/2023 | | | | | | | | |
Site Plans - Trash Enclosures | Need 3rd Subm | ISP Redline Comment Response 4 of 4 | 7/11/2023 | | | | | | | | |
Site Plans - Fence Plans | Need 3rd Subm | ISP Redline Comment Response 3 of 4 | 7/11/2023 | | | | | | | | |
Site Plans - Sign Plans | Need 3rd Subm | ISP Redline Comment Response 2 of 4 | 7/11/2023 | | | | | | | | |
Site Plans - Floor Plans | Need 3rd Subm | ISP Redline Comment Response 1 of 4 | 7/11/2023 | | | | | | | | |
Case Files - Applicant Response - 2nd Review Comments | Need 3rd Subm | ISP 2nd Review Response Letter | 7/11/2023 | | | | | | | | |
Case Files - 2nd Review Comments | Need 3rd Subm | 2nd Review Comments | 12/9/2022 | | | | | | | | |
Case Files - Applicant Response - Technical Review Comments1 | Need 2nd Subm | Comment Response_Letters | 11/14/2022 | | | | | | | | |
Case Files - 1st Review Comments | Need 2nd Subm | 1st Review Comments | 6/10/2022 | | | | | | | | |
Case Files - Response to Pre-app notes | 1st Referral Sent | Acceptance Letter | 5/20/2022 | | | | | | | | |
Case Files - Referral Memo | 1st Referral Sent | Memo | 5/20/2022 | | | | | | | | |
Case Files - Letter of Introduction/Justification | Submit Application | CR LETTER OF INTRODUCTION | 5/13/2022 | | | | | | | | |
Case Files - Title Work | Submit Application | CR MINERAL RIGHTS DRAFT | 4/25/2022 | | | | | | | | |