ROCKY MOUNTAIN RAILPARK ROADWAYS - ISP | Need Tech Subm

All services on this portal will be unavailable from 6 p.m. Thursday, July 10, until the morning of July 11 to provide time to transition development application services to DevPortal.AuroraGov.org. We apologize for any inconvenience this may cause.

Type Phase Title Date Resubmit View
Case Files - Document OneNeed Tech Subm4th Review Comments3/11/2025
Site Plans - Floor PlansNeed Tech SubmCDOT Review Memo - Response2/20/2025
Site Plans - Color and MaterialsNeed Tech SubmCDOT Drainage Conformance Letter2/20/2025
Site Plans - Colored RenderingsNeed Tech SubmCDOT Access Permit2/20/2025
Site Plans - Preliminary Drainage Checklist City Review Need Tech SubmISP Subm 6 Comment-Response and Response Letter2/20/2025
Case Files - 3rd Technical Review Comments Need Tech Subm3rd Technical Review Comments2/5/2025
Case Files - Vicinity MapNeed Tech Subm6th ISP Response Letter & Master License Agreement1/17/2025
Site Plans - Owner's Authorization LetterNeed Tech SubmCDOT access Permit1/8/2025
Master Plan - Master Utilities PlanNeed Tech SubmTIS Responses and Traffic Letter12/20/2024
Master Plan - Master Utilities PlanNeed Tech SubmTIS Responses and Traffic Letter12/20/2024
Case Files - 2nd Technical Review Comments Need Tech Subm2nd Technical Review Comments12/19/2024
Case Files - Title WorkNeed Tech SubmCDOT Access Permit11/15/2024
Case Files - 1st Technical Review Comments Need Tech Subm1st Technical Review Comments11/4/2024
Case Files - Legal DescriptionNeed Tech SubmISP 5th Submittal Comment-Response10/21/2024
Master Plan - Plan NarrativeNeed Tech SubmRMRP-North TIS9/23/2024
Case Files - Administrative Decision Results Letter Need Tech SubmAdministrative Decision Results Letter4/10/2024
Case Files - Applicant Response - Technical Review Comments1Need Tech Subm4th Review Comments3/14/2024
Case Files - Applicant Response - 1st Review Comments Need 3rd SubmRMRP CDOT Response to Comments2/21/2024
Master Plan - Public Improvement PlanNeed 3rd SubmRMRP North Area Memo2/21/2024
Case Files - Applicant Response - Technical Review Comments3Need 3rd SubmRMI ISP Plan Set Response2/21/2024
Case Files - Applicant Response - 3rd Review Comments Need 3rd SubmRMI ISP Response2/21/2024
Case Files - 3rd Review Comments Need 3rd Subm3rd Review Comments10/9/2023
Master Plan - Traffic Impact StudyNeed 3rd SubmRMRP North Area Memo9/26/2023
Case Files - Applicant Response - Technical Review Comments2Need 3rd SubmRMI ISP Response9/15/2023
Case Files - 2nd Review Comments Need 3rd Subm2nd Review Comments3/23/2023
Case Files - CorrespondenceNeed 2nd Submletter2/28/2023
Case Files - 1st Review Comments Need 2nd Subm1st Review Comments9/23/2022
Case Files - Acceptance Letter1st Referral SentDevelopment Application Acceptance Letter9/1/2022
Case Files - Referral Memo1st Referral SentReferral Memo9/1/2022
Site Plans - Traffic Impact ReportSubmit ApplicationTIS8/24/2022
Case Files - Response to Pre-app notesSubmit ApplicationResponse to Pre-apps8/24/2022
Case Files - Letter of Introduction/JustificationSubmit ApplicationRocky Mountain Rail LOI8/24/2022